Route 109 Update for the week of September 18, 2017

The contractor will continue reclaiming Main Street heading east up to number 133 Main Street.  A second crew will continue installing electrical conduit for the street lights and traffic lights.

A second contractor will be installing foundations for the traffic light bases.