Route 109 Update for the week of September 19, 2016

The contractor will continue installing main line drainage pipe in the westbound lane heading east starting from Cottage Street toward Pond Street.

The Gas Company will be charging the new section of pipe at the beginning of the week.  Once completed they will begin making house connections (5 of them).